7/23/2019 - Cold In-Place Recycling Project - Brookside/Hill Farm Area

July 23, 2019 - Cold In-Place Recycling Project – Brookside Area

The Town’s Department of Public Works has the following update on the Cold In-Place Recycling (CIPR) project in the Brookside/Hill Farm area, from July 29 to August 19, 2019.  

We are alerting you to this project and dates, so that you can make arrangements to choose another route during construction.   

CIPR is a method of removing and reusing the existing asphalt surface, which involves grinding off the top 6 inches of the existing asphalt surface and mixing the crushed asphalt with an asphalt recycling agent, and placing it back down with a paver. The Fairfield Public Works Department (203) 256-3176 will be overseeing this project, and the Fairfield Police Department will be overseeing traffic control during all of the construction work. 

Our time schedule is dependent on weather:

Location

7/29

7/30

7/31

8/1

8/2

8/3

8/5

8/6

8/7

8/8

8/9

8/10

8/12

8/13

8/14

8/15

8/16

8/19

Brookside Drive (Phase 1)

Dam to Mill Plain

11,842 SY

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Brookside Drive (Phase 2)

Mill Plain to Mine Hill

10,841 SY

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Hill Farm Road (Phase 3)

Mine Hill to Duck Farm

SY merged into 2nd

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Duck Farm (Phase 4)

Hill Farm to Mill Plain

12,184 SY

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total SY = 34,867

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

PreCon meeting at Mill Plain Road

7/23 at 9:30 am

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Raise trees

(week of 7/22)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Lower structures

Phase 1

Phase 1

Phase 2

Phase 3

Phase 4

?

 

 

 

 

 

 

 

 

 

 

 

 

Mill shoulders, recycle road

 

 

 

 

 

 

Phase 1

Phase 2

Phase 3

Phase 4

Phase 4

 


 

 

 

 

 

Raise structures

 

 

 

 

 

 

 

 

 

Phase 1

Phase 2-3

?

Phase 3-4

 

 

 

 

 

Pave

 

 

 

 

 

 

 

 

 

 

 

 

Phase 1

Phase 2

Phase 3

Phase 4

 

 

Layout line painting

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

ALL AREAS

Line painting (week of 8/19)