7/30/2019 - Update on Southern Connecticut Gas Main Replacement Program – Jennings Area

July 30, 2019 - Update on Southern Connecticut Gas Main Replacement Program – Jennings Area

The Town’s Department of Public Works has the following update on the SCG Main Replacement Program in the Jennings Area.

The Southern Connecticut Gas Company (SCG) has informed the Town of Fairfield of its plans to upgrade the existing natural gas mains in the Jennings neighborhood. The existing mains in this area are generally over 70 years old, low pressure, and cast iron pipes (which tend to be somewhat brittle). SCG is replacing these lines with higher pressure, smaller diameter PVC pipe. This is the current industry standard, and according to SCG this will improve performance and reliability.

When construction is in front of your home, the contractor will make accommodations to allow you to exit your driveway. If you make the contractor (Burns) aware of your schedule as the construction is approaching, the contractor can make the necessary adjustments.

This work will require excavations in the Town road for the main gas line and for the individual home services. The Fairfield Public Works Department (203) 256-3010 will be overseeing this excavation, and also the temporary and permanent pavement restoration work. The Fairfield Police Department will be overseeing traffic control during all of the construction work.

As SCG provides a time schedule when the specific roads are to be under construction, the Town will be posting that information.

Repaving Streets for Gas Main Installation
Spring 2019
Main Gas Line Five Years to Tie In House Services
STREET Working Installed Temp. Paving Status Working Installed Temp. Paving Status Final Paving
Figlar Avenue X X X X
X
Glen Arden Drive X 
X X  X X
Highlawn Road X
X X X X
Jeniford Road X
X X X X
Katona Drive X     X
Nutmeg Lane X     X
Robin Lane X X X X     X
Rock Major Road X
 X  X X X
Sigwin Drive X 
X  X  X X
Sugar Plum Lane X
X X X X

X = Completed phase, X = Working phase