The Town of Fairfield is announcing the start of a Sewer Improvement project on Easton Turnpike (Route 59) starting on Monday, July 13, 2020. The project will run from Jefferson Street to Church Hill Road along Easton Turnpike.
The project includes the replacement of the existing Sewer Pump Station and installing two new forced sewer mains. The purpose of this project is to increase the sewer capacity in the area.
The project (2020-51) was awarded to True Blue Environmental Services LLC. and Kovacs Construction Corporation. The project is expected to be completed by December 2020.
Lane Closure Info:
Traffic will be alternating pattern throughout the construction area Monday through Friday between 8:00AM and 4:00PM
Please contact Chris Rogers in the Sewer Department with any questions (203) 256-3003
Complete plans are available for viewing in the Sewer Department or can be found on the Town website under Bid Archives: https://www.fairfieldct.org/bidresults (2020-51)